The mail received from PEFAA committee on the final proposal is attached below.
dated Feb 11, 2025
Dear Prof Herath / Eng Pitawala / Eng Gunaratne
Good Morning !!!
Please find below PEFAA final proposal for the works to be executed under E76 batch funding for your concurrence.
While appreciating the generous contribution of E 76 batch for the substantial contribution towards our beloved faculty’s diamond Jubilee projects, we express our sincere thanks to the flexibility shown by the E 76 batch,towards agreeing to funding pressing needs to make the faculty’s ambiance great, for the students to make their stay at the faculty memorable.
As already informed, we were planning to do the procurement during the month of December 2024, to take advantage of the generous discounts offered during the festive season.
Bids were invited in early Dec 2024 and once the process was completed, the New Dean – Prof Lilantha Samaranaya, informed us that VC has agreed to allocate funds for rehabilitation of 4 wash rooms ( Two Near the Lecture room # 09 – New Structures lab and the Two near the New library) and that bids will be called on 31 12 2025 at a total budget of Rs. 10.4 m.Dean also requested us to undertake the refurbishing of the 4 single compartment wash rooms in the admin building with the savings.
As a result the material lists had to be re-worked out and bid evaluation was completed on 31 12 2024.
The E 86 batch , which was to fund the male toilet block near the library agreed to fund the Admin building two Ground Floor wash rooms refurbishing (agreed last sunday – 09 02 2025) and we hereby request E 76 batch to undertake the admin building two 1st floor washrooms, as those shall be in a good state at the time of Diamond Jubilee celebrations beginning from 1st. july 2025.
Therefore the final financial scenario for the available E 76 batch funds will be as follows;
Description | Receipt | Expenditure | Balance |
Amount Received from E 76 Batch | 4,185,971.24 | 4,185,971.24 | |
Main Corridor water Proofing (Part Funding. E83 contributing Rs.1.3 m) | 1,000,000.00 | 3,185,971.24 | |
Main Corridor Painting 370 m2@1200/= , under the water proofed area | 444,000.00 | 2,741,971.24 | |
Male Wash Room Near Drawing office 02 | 884,500.00 | 1,857,471.24 | |
Admin Building 1st. Floor male washroom improvement | 671,310.00 | 1,186,161.24 | |
Admin Building 1st. Floor Female washroom improvement | 679,310.00 | 506,851.24 | |
Replacement of 60 concrete Manhhole covers in the faculty | 120,000.00 | 386,851.24 | |
Addl Items for Wash rooms (given in annex 1 attached Below) | 275,500.00 | 111,351.24 | |
Balance available for contingencies | 111,351.24 |
The E 87 batch funded male wash room work near Do1 will commence in a weeks time and once that is completed the E 76 funded wash room near DO2 and admin building 1st Floor wash rooms work will begin in March 2025.. ( From March 10 to April 24 there will be very few students in the faculty and on 24th. April 2025, five batches will be inducted to the faculty and so we want to finish all wash rooms related work by 20 April 2025).
The following documents are also annexed herewith for your kind perusal please.
1 E76 New Proposal 10 02 2025
2 Program for E76 Supported Wash room Improvements
3 Presentation Male washroom (near the DO2)
4 Sanitary ware manufacturers/ Agents in Sri Lanka ver 2
5 Evaluation of bids 31 12 2024 V2
6 Pictures of Chosen Washroom Items from Ms Illyas and Galwala Market
7 A342395000 Victoria WC From ROCA Bathwares
8 Megachem Proposal for main Corridor
9 Drain cover slab costing